"Insufficient capacity" is pretty much what is says - there isn't enough capacity to launch your instance. Normally I'd recommend trying a different Availability Zone.
But in this case, the instance was retired - that is, taken out of service. See the documentation for more information.
Also: m1 instances are very old - the latest generation is now m6 (which were introduced in 2021). In general you'll get better price/performance by using a later generation instance so we encourage you to upgrade.
0
Thank you. I was able to resolve this issue by changing the instance type.
已回答 4 年前