Hi Shreya,
- Files added after the DataSync task starts will not be transferred as part of the running task. If files are added during the prepare phase they may not get scanned. To scan and transfer additional files you can run the DataSync task again. The task will scan the source and destination and only transfer new or changed files.
- A task schedule will define when a task starts, the completion of the task is dependent on the number of files to prepare, transfer, and verify and will run until all phases are complete.
- You can find the start task execution API docuemntion here. [1]
[1] https://docs.aws.amazon.com/datasync/latest/userguide/API_StartTaskExecution.html